A mechanics' lien lets an unpaid contractor, subcontractor or supplier put a claim on the property it improved and, in the end, ask a court to foreclose. Arizona's lien statutes start at A.R.S. 33-981. For homeowners the law has two halves: the general rules, and a strong protection for owner-occupants in 33-1002. This page covers the general rules and points to the owner-occupant page.
Who has lien rights
Every person who labors on, or furnishes professional services, materials, machinery, fixtures or tools for, the construction, alteration or repair of a building or other improvement has a lien on it, whether the work was ordered by the owner or the owner's agent (33-981(A)). Every contractor, subcontractor, architect or builder in charge of the work is the owner's agent for this purpose, so the owner can be liable for the reasonable value of labor or materials furnished to that agent (33-981(B)). A.R.S. 33-983 gives a similar lien to those who improve a lot.
Four limits:
- Unlicensed contractors have no lien rights. A person required to hold an ROC license who doesn't have a valid one can't lien (33-981(C)).
- No preliminary notice, no lien. Anyone required to serve a preliminary 20-day notice may enforce a lien only after serving it and making proof of service (33-981(D)).
- Design professionals need a valid registration and an agreement with the owner, or with an architect, engineer or contractor who has one (33-981(E)-(F)).
- Owner-occupied homes can be liened only by someone with a written contract directly with the owner-occupant (33-1002(B)).
Step 1: The preliminary 20-day notice
Everyone except wage laborers must serve a written preliminary 20-day notice on the owner, the original contractor, any construction lender, and the person they contracted with, as a condition of a valid lien (33-992.01(B)). The notice is due within 20 days after first furnishing labor or materials. A late notice covers only what was furnished in the 20 days before service and afterward (33-992.01(C), (E)). See the preliminary 20-day notice page.
Step 2: Recording the lien
To perfect a lien, the claimant records a notice and claim of lien with the county recorder and then serves a copy on the owner within a reasonable time (33-993(A)). The deadline:
| Situation | Deadline to record |
|---|---|
| Normal case | 120 days after completion |
| Owner recorded a notice of completion | 60 days after recording of the notice |
The notice and claim of lien is made under oath and must include the legal description, the owner's name, the terms of the contract (or a copy if written), the amount after credits, the completion date, and the date the preliminary notice was given, with a copy of the notice and proof of mailing attached (33-993(A)).
When the job counts as "complete"
"Completion" is the earliest of (33-993(C)-(D)):
- 30 days after final inspection and written final acceptance by the agency that issued the building permit, or
- 60 consecutive days with no labor, unless the stop is due to a strike, material shortage or act of God.
If no permit was issued, or the agency doesn't issue final acceptances, completion is the last day labor or materials were furnished.
Shortening the lien period with a notice of completion
After completion, you or your agent may record a notice of completion in the form set out in 33-993(F). That cuts the recording deadline to 60 days. Within 15 days of recording, you must mail a copy, with the recording date and location, by certified or registered mail to the original contractor and everyone who sent you a preliminary notice. Anyone you fail to notify keeps the full 120 days (33-993(I)).
Step 3: Foreclosure within six months
A lien lasts six months after recording unless the claimant files a suit to enforce it and records a notice of pendency of action within that period (33-998(A)). The court may award reasonable attorney fees to the successful party (33-998(B)). If you see no lawsuit after six months, ask a title company or attorney about clearing the expired lien.
Your tools as an owner
Withhold from the general contractor
When a lien is served, you may hold back from what you owe the original contractor the amount shown in the lien. Give the contractor a copy. If the contractor doesn't tell you in writing within 10 days that it disputes the claim, it is treated as agreeing, and you pay the lien claimant when the money comes due (A.R.S. 33-994).
Collect lien waivers with each payment
Arizona prescribes four waiver forms: conditional and unconditional, for progress payments and for final payment. A waiver that doesn't substantially follow the statutory form is unenforceable (A.R.S. 33-1008(D)). Get a conditional waiver from each sub and supplier who sent you a preliminary notice before you pay, and an unconditional one after the payment clears. The preliminary notice itself tells you to do this (33-992.01(C)). An owner and a contractor can't waive other people's lien rights by contract (33-1008(A)).
Require a payment bond
On a larger job, you can require the contractor to furnish a payment bond and record it with the contract. After that, only those with a written contract directly with you can lien the property (A.R.S. 33-1003).
Bond off a disputed lien
After a lien is recorded, you can record a surety bond for 150% of the amount claimed. Recording discharges the lien from the property, and the claimant then pursues the bond instead (A.R.S. 33-1004).
Demand a release
When a lien is paid, the lienholder must issue a release within 20 days. A lien wrongly recorded against an owner-occupant's home must be released within 20 days of the owner's written request. Failure makes the lienholder liable for $1,000 plus actual damages (A.R.S. 33-1006).
Groundless liens
A person who records a lien knowing, or having reason to know, it is groundless or contains a material misstatement is liable for at least $5,000 or three times actual damages, whichever is greater, plus attorney fees. Recording it is a class 5 felony (A.R.S. 33-420).
Licensing ties in
An unpaid supplier or sub can also file an ROC non-payment complaint against a licensed contractor who fails to pay more than $750 when due (A.R.S. 32-1154(A)(10); ROC: Complaint Forms). A contractor may not threaten or retaliate against a sub or supplier for serving a preliminary notice (32-1154(A)(23)).
Related pages
- Owner-occupant lien protection
- Preliminary 20-day notice
- Residential contract requirements
- Contracts and payments topics
Sources
- A.R.S. 33-981, Lien for labor, services or materials
- A.R.S. 33-983, 33-992.01, 33-993, 33-994, 33-998
- A.R.S. 33-1002, 33-1003, 33-1004, 33-1006, 33-1008
- A.R.S. 33-420, False documents
- A.R.S. 32-1154
- ROC: Complaint Forms
Frequently Asked Questions
How long does a contractor have to file a mechanics' lien in Arizona?
Within 120 days after completion of the work, or within 60 days after the owner records a notice of completion (A.R.S. 33-993(A)). Completion is the earlier of 30 days after final inspection and written acceptance by the permit agency, or 60 consecutive days with no labor.
How long is a mechanics' lien valid in Arizona?
Six months after it is recorded, unless the claimant files a suit to enforce it and records a notice of pendency of action within that time (A.R.S. 33-998(A)).
Can an unlicensed contractor put a lien on my house in Arizona?
No. A person required to be licensed as a contractor who does not hold a valid ROC license has no lien rights (A.R.S. 33-981(C)).
How do I get a lien removed after I pay?
The lienholder must issue a release within 20 days after the lien is satisfied. Failing to do so makes it liable for $1,000 plus actual damages (A.R.S. 33-1006). You can also record a surety bond for 150% of the claim to discharge a lien you dispute (33-1004).