If a lumber yard, tile supplier, roofer or plumbing sub mails you a document titled "Arizona Preliminary Twenty Day Lien Notice," it doesn't mean anyone has filed a lien or that your contractor is in trouble. It is a notice Arizona law requires before a sub or supplier can claim a mechanics' lien later. Handling it well is the cheapest way to avoid paying twice. The rules are in A.R.S. 33-992.01.

What the notice is

A preliminary 20-day notice is "one or more written notices from a claimant that are given before the recording of a mechanic's lien" (33-992.01(A)(4)). Except for people performing labor for wages, everyone who furnishes labor, professional services, materials, machinery, fixtures or tools for which a lien may be claimed must serve the notice as "a necessary prerequisite to the validity of any claim of lien" (33-992.01(B)). Without it and proof of service, there's no enforceable lien (A.R.S. 33-981(D)).

The statutory form states, in bold type: "In accordance with Arizona Revised Statutes section 33-992.01, this is not a lien. This is not a reflection on the integrity of any contractor or subcontractor" (33-992.01(D)).

Who sends it and to whom

The claimant serves the notice on (33-992.01(B)):

  • the owner or reputed owner (you),
  • the original contractor (the one you hired),
  • the construction lender, if any, and
  • the person the claimant contracted with.

It goes by first-class mail with a certificate of mailing, or by registered or certified mail, to your home or business address. Service is complete when it's mailed (33-992.01(F)). You may also get an acknowledgment-of-receipt form to sign and return. If you don't return it within 30 days, the sender can prove mailing by affidavit (A.R.S. 33-992.02).

The 20-day deadline

The notice must be given no later than 20 days after the claimant first furnished labor, services or materials to the jobsite (33-992.01(C)). A claimant who serves late doesn't lose everything: it may claim a lien only for what it furnished within the 20 days before service and anything after (33-992.01(E)).

One notice covers the whole job unless the price rises 30% or more over the estimate in the prior notice, or the claimant supplies more than one subcontractor, in which case new notices are needed (33-992.01(G)).

What the notice must contain

33-992.01(C) requires:

  1. A general description of the labor, services or materials and an estimate of the total price.
  2. The claimant's name and address.
  3. The name of the person who ordered them.
  4. A description of the jobsite sufficient to identify it.
  5. A bold-type Notice to Property Owner that unpaid bills may lead to a mechanics' lien and foreclosure on your property, and that you can protect yourself by requiring your contractor to provide conditional and unconditional lien waivers from the person giving the notice.

A notice that otherwise complies isn't defective just because it didn't use bold type or the required type size. That fix was added by Laws 2024, Chapter 89 (33-992.01(I); Laws 2024, ch. 89).

Your 10-day duties

Within 10 days after you receive a preliminary notice, or a written request from someone intending to serve one, you must give that person a written statement with (33-992.01(J)):

  1. the jobsite description,
  2. the owner's name and address,
  3. the original contractor's name and address,
  4. the construction lender's name and address, if any, and
  5. a copy of any recorded payment bond under A.R.S. 33-1003, with the surety and bonding agent's name and address.

If you don't, you can't later defend against the lien on the ground that the notice's information was wrong. If you fail to supply a recorded payment bond, the claimant keeps lien rights to the extent it was prevented from claiming on the bond (33-992.01(K)). The notice tells you this in large type, so read it when it arrives.

What to do, step by step

  1. Don't ignore it. File every preliminary notice with your project papers.
  2. Check the facts. Is it your address? Is the original contractor the one you hired? Respond in writing within 10 days if anything is wrong.
  3. Make a list of every sender. These are the people who could lien your property.
  4. Before each payment, ask your contractor for a conditional waiver and release on progress payment signed by each sender (A.R.S. 33-1008(D)(1)).
  5. After the payment clears, get an unconditional waiver and release on progress payment (33-1008(D)(2)).
  6. At the end, collect conditional and then unconditional final payment waivers (33-1008(D)(3)-(4)).
  7. Consider joint checks payable to the contractor and a supplier for large material deliveries.

A waiver has to substantially follow the statutory form or it isn't enforceable (33-1008(D)). The unconditional forms carry a warning that signing one is enforceable even if the signer wasn't paid, so a careful sub will only sign after the check clears.

If you live in the home

A.R.S. 33-1002 bars liens against an owner-occupant's dwelling except by someone who signed a written contract directly with the owner-occupant. If you qualify, a sub or supplier who only contracted with your contractor can't lien your house even after serving a 20-day notice. The notice still matters: it tells you who is on the job and who to get waivers from, and you may not know for sure whether a court would treat you as an owner-occupant. See owner-occupant lien protection.

Contractors may not discourage notices

A licensed contractor may not prohibit, threaten, retaliate against or intimidate a contractor or supplier for serving a preliminary notice. Doing so is grounds for ROC discipline (A.R.S. 32-1154(A)(23)). A sub or supplier who was required to give the notice and didn't can't recover from the contractor's license bond (A.R.S. 32-1152(E)).

Related pages

Sources

Frequently Asked Questions

Is a preliminary 20-day notice a lien in Arizona?

No. The statutory form says in bold type that it is not a lien and is not a reflection on the integrity of any contractor or subcontractor (A.R.S. 33-992.01). It preserves the sender's right to record a lien later if it isn't paid.

What should I do when I receive a preliminary 20-day notice?

Keep it, check the job address and owner information, and correct any inaccuracies within 10 days. Then ask your contractor for a conditional lien waiver from that sender before each payment and an unconditional waiver after the payment clears (A.R.S. 33-992.01, 33-1008).

What happens if a supplier sends the 20-day notice late?

It can still serve a notice, but it may claim a lien only for labor or materials furnished within the 20 days before service and afterward (A.R.S. 33-992.01(E)).

Does my general contractor have to send me a preliminary notice?

The statute requires every person who furnishes labor, materials or services for which a lien may be claimed to serve the notice, except people working for wages (A.R.S. 33-992.01(B)). The notice is a prerequisite to a valid lien claim.